S.L. 545.36 Art. 4Validity of applications.

En vigueurTexte officiel

(1) An application for the issuing of a guarantee of origin shall cover a period of at least four (4) months.

(2) No application may be made with the Regulator for the issuing of a guarantee of origin in respect of electricity or energy generated outside Malta.

(3) An application for the issuing of a guarantee of origin shall not be considered valid unless the Regulator is provided with:

(a) all the information listed in the First Schedule;

(b) a statement of entitlement submitted by the applicant; and

(c) payment of the application fee for the issuing of the guarantee of origin to be made payable to the Regulator in terms of regulation 10.

(4) A statement of entitlement shall include the following:

(a) a declaration that the producer of electricity or energy is entitled to the issuing of a guarantee of origin; and

(b) a declaration that such person has never submitted and does not intend to submit a request for the issuing of a guarantee of origin to any other person or authority outside Malta with respect to the electricity or energy which is the subject of the application.