Cap. 16 · Civil Code (Cap. 16)

Cap. 16 Art. 538Action to restrain continuation of new work where damage is feared.

Sub-title II

In forceOfficial text

(1) Where a person has reason to apprehend that in consequence of a new work undertaken by any other person either in such other person’s own tenement or in the tenement of others, damage may be caused to an immovable thing possessed by him, he may bring an action demanding that such other person be restrained from continuing such new work, provided this shall not have as yet been completed and one year shall not have elapsed from the commencement thereof.

(2) The court, after summarily taking cognizance of the facts of the claim, may, according to circumstances, either restrain or allow the continuation of such new work, ordering such security as it may deem proper.

(3) Where the continuation of the work has been restrained, such security shall be in respect of the payment of any damages which may be caused by the suspension of the work, in case the opposition to the continuation thereof shall prove to be groundless.

(4) Where the continuation of the work has been allowed, such security shall be for the total or partial demolition of the work, and for the payment of the damages which the plaintiff may suffer, in case he obtains, notwithstanding that the work was allowed to be continued, a final and absolute judgment in his favour.