S.L. 552.32 Art. 4Obligations of the Authority. 4 [S.L.

In KraftAmtlicher Text

(1) The Authority shall:

(a) take all necessary measures to provide project promoters for projects falling within the scope of these regulations with easily available information about its identity;

(b) be the point of contact for information for the REALISATION OF THE TRANS-EUROPEAN TRANSPORT 552.32 NETWORK (TEN-T)

project promoter and for other relevant authorities involved in the procedure leading to the authorising decision for a given project;

(c) provide the project promoter, where required to do so under national law, with the detailed outline of the project application referred to in regulation 6(6), including information on the indicative time-limits relating to the permit-granting procedures, in accordance with the four (4) year time-limit referred to in regulation 5(1);

(d) oversee the timeframe of the permit-granting procedure, and in particular record any extension of the time-limit referred to in regulation 5(3);

(e) if requested, provide guidance to the project promoter concerning the submission of all relevant information and documents, including all the permits, decisions and opinions which have to be obtained and provided for the authorising decision;

(2) The Authority may also provide guidance to the project promoter as to what additional information and, or documents should be delivered in the event that the notification referred to in regulation 6(1) has been rejected.

(3) Sub-regulations (1) and (2) shall be without prejudice to the competence of any other authorities involved in the permit-granting procedure and to the possibility for the project promoter to contact the individual authorities for the specific permits, decisions or opinions which form part of the authorising decision.