S.L. 646.27 Art. 6Prior notice.
In the case of construction sites on which work is scheduled to last longer than thirty (30) working days and on which more than twenty (20) workers are occupied simultaneously, or on which the volume of work is scheduled to exceed five hundred (500) person-days, the client shall communicate a prior notice drawn up in accordance with Schedule III to the Authority, along with any other document or information required by the Authority from time to time, at least four (4) calendar weeks before work starts on the project. Once any work activity on the project commences, a copy of the prior notice in such form as prescribed by the Authority shall be clearly displayed on the construction site by the client and, if necessary, periodically updated by the project supervisor for health and safety matters.