S.L. 623.6 · Avoidance Of Damage To Third Party (S.L. 623.6)

S.L. 623.6 Art. 26Exemptions from submission.

In KraftAmtlicher Text

When before the start of works, the perit in charge of the project certifies, after giving clear reasons, that the structural interventions will not affect third party property, the provisions of regulations 4, 5, 6, 7 and 8 do not apply:

Provided that if requested by the Director, the developer shall submit a method statement and, or a copy of the insurance that covers third parties and, or the bank guarantee and, or the condition report of the contiguous property according to the provisions of the regulations:

Provided also that nothing will prevent, apart from the perit in charge of the project, the appointment of a site technical officer or officers to assume responsibility in terms of these regulations. FIRST SCHEDULE (Regulation 3)