S.L. 552.32 · Streamlining Measures For Advancing The (S.L. 552.32)

S.L. 552.32 Art. 6Organisationof the permit-granting procedure. 6 [S.L.

In KraftAmtlicher Text

(1) The project promoter shall notify the project to the

Authority or, where appropriate, to the joint authority established in accordance with regulation 7(2). The notification of the project by the project promoter shall serve as the start of the permit-granting procedure.

(2) In order to facilitate the assessment of the maturity of the project, the Authority shall carry out the vetting of the notification to define the level of detail of information and the relevant documents which shall be provided by the project promoter when notifying a project. If the project is not mature, the notification shall be rejected by a duly justified decision not later than four (4) months after the receipt of the notification.

(3) The Authority shall take the necessary measures to ensure that project promoters receive general information as a guide to notification, adapted, where relevant, to the mode of transport concerned, containing information about the permits, decisions and opinions that may be required for the implementation of a project.

(4) That information shall, for each permit, decision or opinion, include the following:

(a) general information about the material scope and the level of detail of the information which is to be submitted by the project promoter;

(b) the applicable time-limits or, if there are no such time-limits, indicative time-limits; and

(c) details of the authorities and stakeholders normally involved in consultations linked to the different permits, decisions and opinions.

(5) That information shall be easily accessible to all relevant project promoters, in particular through electronic or physical information portals.

(6) In order to facilitate successful notification, the Authority shall establish a detailed outline of the project application upon request by the project promoter. This detailed outline shall include the following information customised for the individual REALISATION OF THE TRANS-EUROPEAN TRANSPORT 552.32 NETWORK (TEN-T)

project:

(a) the individual stages of the procedure and applicable time-limits or, if there are no such time-limits, indicative time-limits;

(b) the material scope and the level of detail of the information to be submitted by the project promoter;

(c) a list of permits, decisions and opinions which shall be obtained by the project promoter during the permit-granting procedure, in accordance with European Union and national law;

(d) the details of the authorities and stakeholders which shall be involved in connection with the respective obligations, including during the formal phase of the public consultation.

(7) The detailed outline of the project application shall remain valid during the permit-granting procedure. Any amendment to the detailed outline of the project application shall be duly justified.

(8) The Authority may provide the project promoter, on request, with the information supplementing the elements referred to in sub-regulation (6).

(9) When the project promoter has submitted the complete full development application, it shall be validated by the Authority and the authorising decision shall be adopted within the time-limit referred to in regulation 5(1).

(10) The authorities involved in the permit-granting procedure shall notify the Authority that the required permits, decisions, opinions have been issued.