S.L. 545.43 · Promotion Of Energy From Renewable (S.L. 545.43)
S.L. 545.43 Art. 44Simple-notification procedure for grid connections.
PART V
(1) The Regulator shall establish a simple-notification procedure for grid connections by which installations or aggregated production units of renewables self-consumers and demonstration projects, with an electrical capacity of ten point eight kilowatts (10.8 kW) or less, or of a capacity which is equivalent thereto for connections other than three-phase connections, shall be connected to the grid following a notification to the distribution system operator.
(2) The distribution system operator may, within a limited period following the notification referred to in sub-regulation (1), reject the requested grid connection or propose an alternative grid connection point on justified grounds of safety concerns or technical incompatibility of the system components:
Provided that the installation or aggregated production unit may be connected in the case of a positive decision by the distribution system operator, or in the absence of a decision by the distribution system operator within one month following the notification.
(3) The Regulator may allow a simple-notification procedure for installations or aggregated production units with an electrical capacity of above ten point eight kilowatts (10.8 kW) and up to fifty kilowatts (50 kW), provided that grid stability, grid reliability and grid safety are maintained.