S.L. 123.84 · Tax Credits (Owners And Operators Of (S.L. 123.84)
S.L. 123.84 Art. 8Certification of completion by the company.
(1) Upon the completion of the approved project and not later than sixty days therefrom, the company shall deliver to the
Corporation a certificate drawn up by a person who is recognised by the Corporation as competent for this purpose, showing:
(a) the date of completion of the project;
(b) the amount of allowable expenditure.
(2) The company shall, within the time limit set out in sub-rule (1), deliver a copy of the certificate to the Commissioner.
(3) The Commissioner may, after receiving a copy of the certificate, request an independent opinion from the Corporation or any other competent technical person regarding the contents thereof.